If the actual labor rate exceeds the standard labor rate and if the actual labor-hours exceed the number of hours allowed, the total labor flexible budget variance will be:___________.
a. Favorable
b. Unfavorable
c. Equal to labor rate variance
d. Unable to be determined

Respuesta :

Zviko

Answer:

b. Unfavorable

Explanation:

If the Actual labour cost exceed the Budgeted labour cost we will have an unfavourable total labor flexible budget variance.