A construction company can remove 2/3 tons of dirt from a construction site each hour . how long will it take them to remove 30 tons of dirt from the site?

Respuesta :

Americ
Americ Americ
  • 22-06-2018
Set up a ratio to compare the two proportions.

x= number hours to remove 30 ton


(2/3 ton)/ 1 hour= (30 ton)/(x hours)
cross multiply

(2/3)(x)= (1)(30)

2/3x= 30
divide both sides by 2/3

x= 30 ÷ 2/3
to divide by fraction, multiply by reciprocal of 2/3

x= 30 * 3/2
multiply numerators

x= (30*3)/2

x= 90/2

x= 45 hours


ANSWER: It will take 45 hours to remove 30 tons of dirt.

Hope this helps! :)
Answer Link

Otras preguntas

HELP QUICK PLSSSSSSSSS
In a democracy, how is rule of law regarded?
What is the function of each of these structures butterfly and bird wing
A 6.2-L balloon at 55˚C and 615mm Hg is taken to the top of Mt. Everest (-35˚C and 400- mmHg). What is the size of the balloon?
There are ______ essential minerals your body needs.
If the molar mass of zinc is 65.39 g/mol. you have a 65.2g piece of zinc. how many moles of zinc are present?
If 45.0 grams of magnesium hydroxide (fm = 58.33 grams) is reacted, how much water (fm = 18.02 grams) will be produced?group of answer choices13.9 grams72.8 gra
Wesley always estimates his grocery store total as he shops. while at silver street groceries this morning, he estimated his total purchase would be $50, but it
please help I need it
10 points What is an opinion