There are four activities on the critical path, and the standard deviations for their durations are 7, 15, 31, and 6 days. The standard deviation of the duration of the critical path is: a. 1271 b. 35.65 c. 59 d. 7.681 e. 14.75

Relax

Respuesta :

Otras preguntas

what is a simple machine that has two or more simple machines working together
Find the range of values of x such that the quadratic function f(x)=(x+5)^2-16 is positive.
which of the following contributed to the sand creek massacre?
Selective breeding is the process of breeding plants or animals so that they inherit particular traits from their parents. Which of these is not possible with s
You walk 20 m north, then 5 meters south . What is your displacement?
How many Pounds is 18 oz
Why does solomon lie about able to read and write
Which of the following workers are most likely to be part of a union? (Select four answers.) A plumber A policewoman A writer A sales person A financial adv
Members of what religion persecuted the Jews during the inquisition A)Islam B)Hinduism C)Christianity D)Buddhism
Which of the following statements used evidence to support an interpretation? A. When Diego hesitates to confront Ian, it suggests that he still fears his old e